COURANT PROJECT

PROGRESS AND NEXT STEPS

Milestones:

•             Design [2023]

•             Pre-FEED Study [2023]

•             Allocation of a 307 MW electricity block from Hydro-Québec [2024]

•             Submission of the Project Notice to MELCCFP [March 2025]

Upcoming Steps:

•             Ministerial Directive [March 2025]

•             Environmental Impact Study preparation

•             Submission of the Impact Study to MELCCFP

•             Public information period

•             BAPE (Bureau of Public Hearings on the Environment) Inquiry and Public Hearing

•             MELCCFP Environmental Analysis

•             BAPE report

•             Quebec Government decision

•             Start of construction work

•             Commissioning of the complex